Performing PJM Load Deliverability Test Analysis

Capacity emergency transfer limit (CETL) analysis using MUST and PSS/E. Perform voltage and thermal load deliverability tests. Key Deliverable: POWER-tek assisted PJM to obtain assurance that the internal and external firm capacity resources can be delivered to the area experiencing a localized capacity emergency by carrying out the ‘Deliverability to the Load’ test. The objective of this work is to determine the transfer capability the actual ability of the transmission system to support deliveries of energy to an electrical area experiencing such a capacity emergency.