Grid System Operational and Dispatch Analysis for Fauji Kabirwala Plant Testing

Objectives/background/needs:  This plant was under capacity and reliability testing.  After many unsuccessful tests, they wanted to simulate the plan and grid system to investigate the issues and provide recommendations for successful capacity and reliability tests.

Key deliverables and solution provided: Steady state and Dynamic simulations/analysis for reactive power capability testing. Recommended solution through transmission network changes & equipment setting adjustments to remove different bottlenecks for reactive power capability acceptance tests for different grid operating scenarios.  Short circuit analysis to determine grid system strength around FKPCL plant.

Determine plants merit order through economic dispatch analysis.  Support for solution implementation for reactive power tests.